Kirby Drive Improvement Project Update

May 14, 2010

The City of Houston’s contractor has established the construction zone with appropriate traffic control between the city limit line and an area just south of Sunset Blvd.

The first phase of this segment is substantially complete with the storm box installation and westside paving.

At the present, lane separation and closure to the eastside lanes has occurred to facilitate the paving from approximately Sunset Blvd. north to the city limits.

The contractor initially anticipated being complete with all construction activity on Kirby Drive adjacent to our city limits by March 31, 2010, however due to recent adverse weather conditions, this date has been revised to May 31, 2010.

InstantNewsWestu Staff

View more articles Subscribe
menu