The final lanes of Bellaire Blvd. between Stella Link and Weslayan Street have been paved. The placement of storm water boxes continues northbound on College Avenue, and has progressed from Riley Street through College Avenue’s intersection with Southwestern Street.

 

Beginning Monday or Tuesday of next week, April 6 or 7, all lanes of Riley Street will be reopened to traffic with the construction zone being on College Avenue exclusively. Northbound traffic on College Avenue will be detoured between Riley Street and Villanova Street. As construction proceeds north, traffic control will move with the construction zone. A construction zone is in the process of being established on College Avenue, with periods of “one way” and “controlled access.”

 

The revised tentative constructive schedule is as follows.

 

Weslayan Street from Riley Street to Marquette Street – January 2009 to March 2009

Riley Street from Weslayan Street to College Ave. – February 2009 to April 2009

College Ave. from Riley Street to University Blvd. – April 2009 to August 2009